The Point at Beaufont Unit Renovations
Pegasus
75% Complete
Project Progress
75% Progress

100% Timing

Start Date
April 1, 2023
End Date
September 30, 2024
46/47
Complete Phases
209/246
Complete Tasks
Project Description

Renovate units at The Point at Beaufont. 

Edit Description
Documents

No documents at this time.

Icebox
Backlog
In Progress
Review/QA
Completed
Add List
Edit List
Phases Board
46 / 47 Completed
Unit 6829E 0 5 / 5 0
100%
Description

Test color unit. Using color Alabaster on walls and cabinets. 

10/5: Picking up keys and starting unit. 

10/12 complete

No documents attached to this phase.
Unit 6829D 0 5 / 5 0
100%
Description

9/26: Got keys and demoed

10/4: Finishing backsplash, cabinet doors and paint touch ups. Then complete. 

No documents attached to this phase.
Unit 6905E 0 5 / 6 0
100%
Description
6/2/23: Received keys, demoed and painted today. 6/6/23: Missing doors and reno kit 6/8/23: Will check office tomorrow for missing doors and kit. 6/15/23: Still missing doors 6/20/23: Still missing doors and flooring. 6/27/23: Still missing doors. 7/19/23: Still missing doors 7/27/23: Still missing doors 8/2/23: Still missing doors 8/10/23: Still missing doors, going to try to make something work tomorrow. 8/11/23: Finished, pending walk.
No documents attached to this phase.
Unit 6913D 0 5 / 6 0
100%
Description
6/14/23: received keys 6/20/23: Missing 3 doors 6/27/23: Missing 3 doors still 7/26/23: Doors arrived and installed.
No documents attached to this phase.
Unit 6915B 0 5 / 6 0
100%
Description
6/27/23: Missing doors, installing kit tomorrow. 7/10/23: Done. Pending walk.
No documents attached to this phase.
Unit 6911A 0 5 / 6 0
100%
Description
6/27/23: Missing doors. Unit complete after installation. 7/19/23: Still missing doors 7/27/23: Doors still on order. 8/2/23:  Unit complete, pending walk.
No documents attached to this phase.
Unit 6905C 0 5 / 6 0
100%
Description
6/13/23: Received keys 6/20/23: Missing doors and flooring. 6/27/23: Still missing doors and flooring 7/27/23: Doors still on order 7/28/23: Unit complete
No documents attached to this phase.
Unit 6815H 0 6 / 6 0
100%
Description
7/7/23: Emailed about no power 7/19/23: Just missing a few doors 7/27/23: Unit complete, pending walk.
No documents attached to this phase.
Unit 6817H 0 6 / 6 0
100%
Description
7/27/23: Unit complete, pending walk.
No documents attached to this phase.
Unit 6819A 0 6 / 6 0
100%
Description
7/19/23: Just missing a few doors 7/27/23: Unit complete and cleaned, pending walk.
No documents attached to this phase.
Unit 6931F 0 6 / 6 0
100%
Description
7/20/23: Just missing a few doors 7/27/23: Unit complete, pending walk.
No documents attached to this phase.
Unit 6911H 0 6 / 6 0
100%
Description
7/19/23: Just missing a few doors. 7/27/23: Doors on order, supposed to be delivered today or tomorrow. 8/2/23: Missing 1 cabinet drawer face, will try to find one in shop. 8/10/23: Unit complete, pending walk
No documents attached to this phase.
Unit 6831B 0 6 / 6 0
100%
Description
7/7/23: Got keys 7/23/23: Unit complete
No documents attached to this phase.
Unit 6913G 0 6 / 6 0
100%
Description
7/7/23: Got keys 7/19/23: Mostly complete, missing 87 inch blinds, and a few cabinet doors. 7/27/23: Cabinet doors on order, should be in this week. Still need blinds. 8/4/23: Unit complete
No documents attached to this phase.
Unit 6921G 0 4 / 6 0
100%
Description
7/7/23: Got keys emailed about not having power 7/19/23: Mostly complete. Need 2 passage door locks, 2 sets of 58 inch blinds, 1 gfi for bathroom, and cabinet doors. 7/27/23: Just need to sort out cabinet door situation. Currently measuring. 7/31/23: Unit complete
No documents attached to this phase.
Unit 6815B 0 5 / 6 0
100%
Description
Tenant moves out 6/1/23, will attempt to get keys 6/2/23 6/2/23: Tenant has not moved out yet. Will get with front office Monday 6/5. 6/6/23: Renovation on hold until July. 7/7/23: Received keys 7/13/23: Went to start and someone is still living here. 7/17/23: Finally received keys, site is trashing out unit. 7/27/23: Nearly complete. Missing a few items, going to Lowes to purchase. 8/2/23: Unit complete, needs flooring.
No documents attached to this phase.
Unit 6847D 0 5 / 5 0
100%
Description
7/19/23: Started unit 7/27/23: Complete, pending walk.
No documents attached to this phase.
Unit 6849G 0 5 / 5 0
100%
Description
7/14/23: Got keys 7/27/23: Unit complete, pending walk
No documents attached to this phase.
Unit 6917B 0 4 / 5 0
100%
Description
7/14/23: Got keys 7/27/23: Missing 4 doors, everything else complete. 8/2/23: Still missing doors 8/10/23: Still missing doors 8/22/23: Unit complete, pending walk.
No documents attached to this phase.
Unit 6837H 0 5 / 5 0
100%
Description
7/26/23: Got keys 8/2/23:  Unit complete, needs flooring.
No documents attached to this phase.
Unit 6845D 0 5 / 5 0
100%
Description
8/1/23: Got keys 8/10/23: Unit complete, pending walk.
No documents attached to this phase.
Unit 6819H 0 5 / 5 0
100%
Description
8/1/23: Got keys 8/10/23: Unit complete, pending walk.
No documents attached to this phase.
Unit 6805D 0 5 / 5 0
100%
Description
8/10/23: Received keys 8/22/23: Ready for carpet, unit finished pending walk.
No documents attached to this phase.
Unit 6845C 0 0 / 0 0
100%
Description
8/18/23: Unit complete, pending walk.
No documents attached to this phase.
Unit 6825H 0 0 / 0 0
100%
Description
8/18/23: Unit complete, pending walk.
No documents attached to this phase.
Unit 6919A 0 5 / 5 0
100%
Description

8/23/23: Got keys

8/24/23: Demoed and painted

8/28/23: Unit needs carpet, unit complete, pending walk. 

No documents attached to this phase.
Unit 6923C 0 5 / 5 0
100%
Description

8/23/23: Got keys

8/24/23: Demoed and painted 

8/31/23: Unit will be completed by Saturday 9/2

9/6: Complete, pending walk

No documents attached to this phase.
Unit 6907D 0 5 / 5 0
100%
Description

8/30: Got keys

9/6: Should be finished Thursday

9/8: Finished pending walk

No documents attached to this phase.
Unit 6851E 0 0 / 0 0
100%
Description

9/5: Got keys, demoed

9/15: Cabinet doors not delivered yet, everything else done. 

9/19: Unit complete, pending walk. 

No documents attached to this phase.
Edit Phase
Add Phase
Update Status
Document Status Updated
Notifications have been sent.