The Point at Beaufont Unit Renovations
Pegasus
75% Complete
Project Progress
75% Progress

100% Timing

Start Date
April 1, 2023
End Date
September 30, 2024
46/47
Complete Phases
209/246
Complete Tasks
Project Description

Renovate units at The Point at Beaufont. 

Edit Description
Documents

No documents at this time.

Project Delays
No delays recorded on this project.
Icebox
Backlog
In Progress
Review/QA
Completed
Add List
Edit List
Phases Board
46 / 47 Completed
Unit 6829E 0 5 / 5 0
100%
Description

Test color unit. Using color Alabaster on walls and cabinets. 

10/5: Picking up keys and starting unit. 

10/12 complete

No documents attached to this phase.
Unit 6829D 0 5 / 5 0
100%
Description

9/26: Got keys and demoed

10/4: Finishing backsplash, cabinet doors and paint touch ups. Then complete. 

No documents attached to this phase.
Unit 6905E 0 5 / 6 0
100%
Description
6/2/23: Received keys, demoed and painted today. 6/6/23: Missing doors and reno kit 6/8/23: Will check office tomorrow for missing doors and kit. 6/15/23: Still missing doors 6/20/23: Still missing doors and flooring. 6/27/23: Still missing doors. 7/19/23: Still missing doors 7/27/23: Still missing doors 8/2/23: Still missing doors 8/10/23: Still missing doors, going to try to make something work tomorrow. 8/11/23: Finished, pending walk.
No documents attached to this phase.
Unit 6913D 0 5 / 6 0
100%
Description
6/14/23: received keys 6/20/23: Missing 3 doors 6/27/23: Missing 3 doors still 7/26/23: Doors arrived and installed.
No documents attached to this phase.
Unit 6915B 0 5 / 6 0
100%
Description
6/27/23: Missing doors, installing kit tomorrow. 7/10/23: Done. Pending walk.
No documents attached to this phase.
Unit 6911A 0 5 / 6 0
100%
Description
6/27/23: Missing doors. Unit complete after installation. 7/19/23: Still missing doors 7/27/23: Doors still on order. 8/2/23:  Unit complete, pending walk.
No documents attached to this phase.
Unit 6905C 0 5 / 6 0
100%
Description
6/13/23: Received keys 6/20/23: Missing doors and flooring. 6/27/23: Still missing doors and flooring 7/27/23: Doors still on order 7/28/23: Unit complete
No documents attached to this phase.
Unit 6815H 0 6 / 6 0
100%
Description
7/7/23: Emailed about no power 7/19/23: Just missing a few doors 7/27/23: Unit complete, pending walk.
No documents attached to this phase.
Unit 6817H 0 6 / 6 0
100%
Description
7/27/23: Unit complete, pending walk.
No documents attached to this phase.
Unit 6819A 0 6 / 6 0
100%
Description
7/19/23: Just missing a few doors 7/27/23: Unit complete and cleaned, pending walk.
No documents attached to this phase.
Unit 6931F 0 6 / 6 0
100%
Description
7/20/23: Just missing a few doors 7/27/23: Unit complete, pending walk.
No documents attached to this phase.
Unit 6911H 0 6 / 6 0
100%
Description
7/19/23: Just missing a few doors. 7/27/23: Doors on order, supposed to be delivered today or tomorrow. 8/2/23: Missing 1 cabinet drawer face, will try to find one in shop. 8/10/23: Unit complete, pending walk
No documents attached to this phase.
Unit 6831B 0 6 / 6 0
100%
Description
7/7/23: Got keys 7/23/23: Unit complete
No documents attached to this phase.
Unit 6913G 0 6 / 6 0
100%
Description
7/7/23: Got keys 7/19/23: Mostly complete, missing 87 inch blinds, and a few cabinet doors. 7/27/23: Cabinet doors on order, should be in this week. Still need blinds. 8/4/23: Unit complete
No documents attached to this phase.
Unit 6921G 0 4 / 6 0
100%
Description
7/7/23: Got keys emailed about not having power 7/19/23: Mostly complete. Need 2 passage door locks, 2 sets of 58 inch blinds, 1 gfi for bathroom, and cabinet doors. 7/27/23: Just need to sort out cabinet door situation. Currently measuring. 7/31/23: Unit complete
No documents attached to this phase.
Unit 6815B 0 5 / 6 0
100%
Description
Tenant moves out 6/1/23, will attempt to get keys 6/2/23 6/2/23: Tenant has not moved out yet. Will get with front office Monday 6/5. 6/6/23: Renovation on hold until July. 7/7/23: Received keys 7/13/23: Went to start and someone is still living here. 7/17/23: Finally received keys, site is trashing out unit. 7/27/23: Nearly complete. Missing a few items, going to Lowes to purchase. 8/2/23: Unit complete, needs flooring.
No documents attached to this phase.
Unit 6847D 0 5 / 5 0
100%
Description
7/19/23: Started unit 7/27/23: Complete, pending walk.
No documents attached to this phase.
Unit 6849G 0 5 / 5 0
100%
Description
7/14/23: Got keys 7/27/23: Unit complete, pending walk
No documents attached to this phase.
Unit 6917B 0 4 / 5 0
100%
Description
7/14/23: Got keys 7/27/23: Missing 4 doors, everything else complete. 8/2/23: Still missing doors 8/10/23: Still missing doors 8/22/23: Unit complete, pending walk.
No documents attached to this phase.
Unit 6837H 0 5 / 5 0
100%
Description
7/26/23: Got keys 8/2/23:  Unit complete, needs flooring.
No documents attached to this phase.
Unit 6845D 0 5 / 5 0
100%
Description
8/1/23: Got keys 8/10/23: Unit complete, pending walk.
No documents attached to this phase.
Unit 6819H 0 5 / 5 0
100%
Description
8/1/23: Got keys 8/10/23: Unit complete, pending walk.
No documents attached to this phase.
Unit 6805D 0 5 / 5 0
100%
Description
8/10/23: Received keys 8/22/23: Ready for carpet, unit finished pending walk.
No documents attached to this phase.
Unit 6845C 0 0 / 0 0
100%
Description
8/18/23: Unit complete, pending walk.
No documents attached to this phase.
Unit 6825H 0 0 / 0 0
100%
Description
8/18/23: Unit complete, pending walk.
No documents attached to this phase.
Unit 6919A 0 5 / 5 0
100%
Description

8/23/23: Got keys

8/24/23: Demoed and painted

8/28/23: Unit needs carpet, unit complete, pending walk. 

No documents attached to this phase.
Unit 6923C 0 5 / 5 0
100%
Description

8/23/23: Got keys

8/24/23: Demoed and painted 

8/31/23: Unit will be completed by Saturday 9/2

9/6: Complete, pending walk

No documents attached to this phase.
Unit 6907D 0 5 / 5 0
100%
Description

8/30: Got keys

9/6: Should be finished Thursday

9/8: Finished pending walk

No documents attached to this phase.
Unit 6851E 0 0 / 0 0
100%
Description

9/5: Got keys, demoed

9/15: Cabinet doors not delivered yet, everything else done. 

9/19: Unit complete, pending walk. 

No documents attached to this phase.