Starboard Townhomes
Community Investment Group
50% Complete
Project Progress
50% Progress

100% Timing

Start Date
May 15, 2023
End Date
December 31, 2023
7/10
Complete Phases
171/240
Complete Tasks
Project Description

Renovate units at Starboard Townhomes

Units 540A, 540B, 540C all complete. Focusing on 540 D and E. 

Edit Description
Documents

No documents at this time.

Project Delays
No delays recorded on this project.
New To-dos
Icebox
Backlog
In Progress
Review/QA
Completed
Add List
Edit List
Phases Board
Expand Discussions | 7 / 10 Completed
540 A 0 24 / 24 0
100%
Description
Updated pictures of unit 6/6/23 https://ibb.co/album/0q9dgp
No documents attached to this phase.
Leave a Reply
Your email address will not be published. Required fields are marked *

540 B 0 24 / 24 0
100%
Description
Updated photos of unit 6/6/23 https://ibb.co/album/m9BKYk    
No documents attached to this phase.
Leave a Reply
Your email address will not be published. Required fields are marked *

540 C 0 24 / 24 0
100%
Description
Updated photos of unit 6/6/23 https://ibb.co/album/xmmRKV
No documents attached to this phase.
Leave a Reply
Your email address will not be published. Required fields are marked *

540 D 0 2 / 24 0
35%
Description
Updated photos of unit 6/6/23 https://ibb.co/album/yBX0kD
No documents attached to this phase.
Leave a Reply
Your email address will not be published. Required fields are marked *

540 E 0 2 / 24 0
35%
Description
Updated photos of unit 6/6/23 https://ibb.co/album/3yBvcy
No documents attached to this phase.
Leave a Reply
Your email address will not be published. Required fields are marked *

Unit 550A 0 24 / 24 0
100%
Description
Completed 6/21
No documents attached to this phase.
Leave a Reply
Your email address will not be published. Required fields are marked *

Unit 550C 0 24 / 24 0
100%
Description
Unit completed 6/21
No documents attached to this phase.
Leave a Reply
Your email address will not be published. Required fields are marked *

Unit 547E 0 23 / 24 0
100%
Description
Unit completed 6/22.
No documents attached to this phase.
Leave a Reply
Your email address will not be published. Required fields are marked *

Unit 546A 0 24 / 24 0
100%
Description
Unit Completed 6/23
No documents attached to this phase.
Leave a Reply
Your email address will not be published. Required fields are marked *

Unit 10 0 0 / 24 0
10%
No documents attached to this phase.
Leave a Reply
Your email address will not be published. Required fields are marked *

Edit Phase
Add Phase
Project Discussion No discussions posted at this time

Your email address will not be published. Required fields are marked *

Update Status
Document Status Updated
Notifications have been sent.