Granby Crossing
Pegasus
60% Complete
Project Progress
60% Progress

100% Timing

Start Date
May 24, 2023
End Date
September 26, 2024
17/21
Complete Phases
71/84
Complete Tasks
Project Description

Renovate units at Granby Crossing Apartments

4/18 - Still having issues receiving fan rods for 3rd floor apartments. Need 18 inch brushed nickel with 1/2 inch diameter. 416 received an incomplete reno kit, Chadwell says items were backordered and will be in next week.

4/24 - Still waiting on the rest of the reno kit and cabinet doors for 416. 

Edit Description
Documents

No documents at this time.

Icebox
Backlog
In Progress
Review/QA
Add List
Edit List
Phases Board
17 / 21 Completed
Unit 422 0 1 / 4 0
20%
Description

6/28 Got keys

No documents attached to this phase.
Unit 717 0 1 / 4 0
20%
Description

Keys: 6/28

No documents attached to this phase.
Unit 124 0 1 / 4 0
20%
Description

Keys 6/25

No documents attached to this phase.
Unit 716 0 1 / 4 0
20%
Description

Keys 6/25

No documents attached to this phase.
Unit 714 0 4 / 4 0
100%
Description

Keys 6/17

No documents attached to this phase.
Unit 212 0 4 / 4 0
100%
Description

Keys 6/13

No documents attached to this phase.
Unit 719 0 4 / 4 0
100%
Description

Keys 6/13

No documents attached to this phase.
Unit 607 0 4 / 4 0
100%
Description

Keys 6/10

No documents attached to this phase.
Unit 508 0 4 / 4 0
100%
Description

Picking up keys 6/4

No documents attached to this phase.
Unit 119 0 4 / 4 0
100%
Description

Got keys: 5/22

6/3: Need countertops, flooring and appliances. 

No documents attached to this phase.
Unit 224 0 4 / 4 0
100%
Description

6/4: Need flooring and appliances. 

No documents attached to this phase.
Unit 707 0 4 / 4 0
100%
Description

5/28: Got keys

No documents attached to this phase.
Unit 210 0 4 / 4 0
100%
Description

Completed: 5/31

No documents attached to this phase.
Unit 304 0 4 / 4 0
100%
No documents attached to this phase.
Unit 416 0 4 / 4 0
100%
No documents attached to this phase.
Unit 118 0 4 / 4 0
100%
No documents attached to this phase.
Unit 512 0 3 / 4 0
100%
No documents attached to this phase.
Unit 319 0 4 / 4 0
100%
No documents attached to this phase.
Unit 424 0 4 / 4 0
100%
No documents attached to this phase.
Unit 214 0 4 / 4 0
100%
No documents attached to this phase.
Unit 305 0 4 / 4 0
100%
No documents attached to this phase.
Edit Phase
Add Phase
Update Status
Document Status Updated
Notifications have been sent.